Planning the work after a house rewire
By Ian Walsh, Renew Electrical, 22 November 2026
Rewire first, while the house is empty. Then the chases are plastered and the plaster dries for a few days before painting. Floors that were lifted go back once the cabling is in, and new carpets or wooden floors go down last. Plan the kitchen and bathroom layout with the electrician at the survey, so the circuits go where you want them.
The rewire is usually the first big job in an older house, and the one everything else waits for. Get the order right and you move into a finished house instead of living around the work.
The usual order
- Survey and quote. As soon as you have access, so the rewire can be booked for when the house is empty.
- The rewire. Usually 3 to 10 working days on site, depending on the house. The house needs to be empty while it’s done.
- Plastering the chases. With me it’s on the quote (it comes off if you have your own plasterer).
- Drying time. A few days before the walls can be painted.
- Painting and decorating. Not part of an electrician’s job. Book your painter for after the plaster has dried.
- Floors. New carpets or wooden floors go down last, so they aren’t lifted or marked during the work.
- Kitchen and bathroom fit-out. Plan these with me at the survey, so the sockets, cooker and shower circuits are where you want them.
- Moving in, with your Safe Electric completion certificate in the house papers.
If you have your own plasterer or builder
That’s common: about half my customers take the plastering off the quote. If you do, I come in when the house is fully ready for the electrics, so I’m not doing half the job and coming back. Tell me at the survey who else is working in the house and when, and we’ll fit around them.
Things to decide before the survey
- Where you want extra sockets, USB sockets, outside lights and TV points.
- Where the kitchen appliances will go, if there’s a new kitchen coming.
- Whether you’ll want an EV charger later. It’s easier to plan the cable now.
- Whether you have your own plasterer, so it can come off the quote.
Painting, floors and budget
My quote covers the electrical work and plastering the chases. Painting, new floors and kitchen work are separate trades. Ask for their quotes early so they can follow straight on, and budget for them alongside the rewire. If you need a painter, I can refer you to one.
Book the survey early
If you’re buying, send us the size of the house and the electrical part of your surveyor’s report on WhatsApp for a rough range before you have the keys, then book the free survey for as soon as you have access. More on the timing in rewire an older house before you move in.
Quick answers
Should I rewire before or after a new kitchen?
Before. Doing the wiring first means the new kitchen, floors and decorating aren't disturbed later. Bring the kitchen layout to the survey so the cooker and appliance circuits go where you want them.
When can I paint after a rewire?
Once the plaster over the chases has dried, usually a few days. Your painter will tell you when it's ready.
What happens to my floors during a rewire?
Floorboards are lifted in places to run cable between floors. I go through what gets lifted, and how it's put back, at the survey.